Answer :
Answer:
a. $184,500
Explanation:
The computation of the cost of units transferred out is shown below:
Total unit cost is
= $1.50 + $0.75
= $2.25 per unit
And, Unit completed and transferred out = 82000
So, Cost of unit completed and transferred out is
= 82,000 units × $2.25
= $184,500
hence, the correct option is a.