Answer :
Answer:
6 days
Step-by-step explanation:
2 boys that each work half as fast as the men is equivalent to having one extra man. So instead of 3 men we have 4. 4/3 the manpower means 3/4 the time. 3/4 of 8 is 6.
Answer:
6 days.
Step-by-step explanation:
The 3 men can build 1/8 of a wall in 1 day.
So 1 man can build 1/24 wall in 1 day.
So 1 boy can build 1/48 in 1 day and 2 boys can build 1/24 wall in 1 day.
So we have the equivalent of 4 men working and they can build 4 * 1/24
= 1/6 of a wall per day
So the answer is 6 days.