Answer :

Answer:

6 weeks

Step-by-step explanation:

Set up a proportion where x is the amount of time with 12 pupils:

[tex]\frac{4}{2}[/tex] = [tex]\frac{12}{x}[/tex]

Cross multiply and solve for x:

4x = 24

x = 6

So, it will take 12 pupils 6 weeks to complete the job.