Answer :
Answer:
$7,326,000
Explanation:
Calculation for what is the projected total cost
Using this formula
Projected total cost=(Projected hours*Variable cost per hour of labor)+Fixed cost
Let plug in the formula
Projected total cost=(204,000 hours*$35)+$186,000
Projected total cost=$7,140,000+$186,000
Projected total cost=$7,326,000
Therefore the projected total cost will be $7,326,000