the water behind hoover dam in nevada is 206 m higher than the colorado river below it. at what rate must water pass through the hydraulic turbines of this dam to produce 100 mw of power if the turbines are 100 percent efficient

Answer :

Answer:

the required mass flow rate is 49484.37 kg/s

Explanation:

Given the data in the question;

we first determine the relation for mass flow rate of water that passes through the turbine;

so the relation for net work on the turbine due to the change in potential energy considering 100% efficiency is;

[tex]W_{net}[/tex] = m ( Δ P.E )

so we substitute (gh) for ( Δ P.E );

[tex]W_{net}[/tex] = m (gh)

m = [tex]W_{net}[/tex] / gh

so we substitute our given values into the equation

m = 100 MW / ( 9.81 m/s²) × 206 m

m = ( 100 MW × 10⁶W/MW) / ( 9.81 m/s²) × 206 m

m = 10 × 10⁷ / 2020.86

m = 49484.37 kg/s

Therefore, the required mass flow rate is 49484.37 kg/s

Go Teaching: Other Questions