Answer :
Question Completion:
Completed by August 1, 2021 August 8, 2021 August 15, 2021 After August 15, 2021 Probability 70 % 20 6 4.
Answer:
Pina Corp.
The transaction price for the contract, assuming Pina has limited information with which to develop a reliable estimate of completion by the August 1, 2021, deadline is:
= $921,300.
Explanation:
Data and Calculations:
Completed by Probability
August 1, 2021 70%
August 8, 2021 20%
August 15, 2021 6%
After August 15, 2021 4%
Total = 100%
Contract price = $921,300
Performance bonus = $156,000
Expected completion date = August 1, 2021
Reduction of bonus per week if completion is delayed = $52,000
After August 15 (three weeks of non-completion), there is no performance bonus because it would have been reduced to $0 ($156,000/$52,000 = 3 weeks).