Answer: $17,000
Explanation:
Labour efficiency variance = Standard rate * (Standard hours - Actual hours )
Standard hours:
= Standard labor-hours allowed per unit * Number of units produced in period
= 3 * 15,000
= 45,000 hours
Labor efficiency variance = 17 * (45,000 - 44,000)
= $17,000 Favorable
Favorable because the standard amount is higher than the actual amount.