Answer :
Answer:
Results are below.
Explanation:
To calculate the direct material rate and quantity variance, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (0.55 - 0.54)*4,000
Direct material price variance= $40 favorable
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (0.75*4,800 - 3,588)*0.55
Direct material quantity variance= $6.6 favorable
Finally, the total variance:
Total direct material variance= 40 + 6.6= $46.6 favorable