Answer :
Answer:
Standard cost Supplies= $3,480
Explanation:
Giving the following information:
The cost formula for catering supplies is $400 per month plus $82 per job plus $10 per meal.
The company expected its activity in September to be 20 jobs and 144 meals.
To calculate the total budgeted cost, we need to multiply the standard cost for the planned production:
Standard cost Supplies= 400 + (82*20) + (10*144)
Standard cost Supplies= $3,480