Answer :

There are different kinds of program. In the program evaluation and review technique (PERT), a delay in a critical path will cause the entire project to fall behind.

What is program evaluation and review technique?

Program Evaluation Review Technique (PERT) is known to be a statistical tool that is often used in project management.

It is said to be created so as to help analyze and represent the tasks that is used in completing a said project. ​If any task along a critical path is said to fall behind a specific schedule, the entire project have to be delayed.

learn more about  program evaluation from