Jus de Fruit Co. has set up for automated production of its new bottled Triple Berry Colada. Six samples were taken during the first week of production. The OM team wants to monitor the central tendency of the process. What chart should they use? Is the process in control?

Answer :

The X bar chart will allow the team to monitor the central tendency of the process although the process will not be in control.

What is the X bar chart?

This refers to a Shewhart control chart that are used to monitor the arithmetic means of successive samples of constant size.

Hence, the X bar chart will allow the OM team to monitor the central tendency of the process although the process will not be in control.

Therefore, the Option B is correct.