Once the project schedule and project budget are approved they become the _____ Group of answer choices project plan derivative plan schedule plan baseline plan actual plan

Answer :

Once the project schedule and project budget are approved they become the baseline plan. This is further explained below.

What is the baseline plan?

Generally,  Project management baselines are the established points from which further planning is done.

In conclusion, As soon as the project timeline and budget are greenlit, they constitute the foundation of the project.

Read more about baseline plan