Answer :

Answer: t = 6.67 hours

Explanation:

From the information given,

Diego can lay a slab of concrete in 15 hours. This means the rate at which he can lay the slab = 1/15

Luis can do it in 12 hours. The rate at which he lay the slab = 1/12

Let t represent the number of hours it will take them to work together. It means that the rate at which they can lay the slab together is 1/t

Since the rates are independent of each other, then

1/15 + 1/12 = 1/t

The lowest common multiple of the denominator is = 60

Thus,

(4 + 5)/60 = 1/t

9/60 = 1/t

By taking reciprocal of both sides,

t = 60/9

t = 6.67

It will take 6.67 hours for them to work together